Work Package 1: Project Management, Administration, Information and Communication

Methodology: The design and implementation of appropriate management tools for the coordination of the consortium and communication of the desk study activities, networking of all partners and monitoring and evaluation to fully reach the objectives set by the desk study.
Activities:
1.1. Preparation of the partners´ Consortium Agreement and Data Management Plan (DMP)
1.2. Kick –Off Meeting in Banjul
1.3. Mid-project conference and project meeting in Banjul
1.4. Submission of the final Desk Study Report to BMBF
Deliverables
D.1.1. Partners´ Consortium an Data Management Plan ready (M3)
D.1.2. Kick –Off Meeting held in Banjul (M3)
D.1.3. Mid-project conference and project meeting in Banjul (M12)
D.1.4. Submission of the final Desk Study Report to BMBF (M24)
Strategic benefit: a sound project management framework.